Jump to content

drain tile


Recommended Posts

Have your contractor add a footer under the wall 4ft. at a time skipping every other 4ft. section. Make sure the contractor uses dobies and #4 rebar to reinforce the new footer and extends the rebar into the earth at either end of the footing excavations so that when the area between the first set of new footers is excavated there will be something to tie into. Use Form-a-Drain for the form on the inside. Wait a month for the first set of blocks to cure and then go back and excavate the earth between each of those 4ft. sections and repeat the process until you've filled in all area between blocks. Connect your drain tile to the Form-a-Drain.

ONE TEAM - ONE FIGHT!!!

Mike

Link to comment
Share on other sites

Have your contractor add a footer under the wall 4ft. at a time skipping every other 4ft. section. Make sure the contractor uses dobies and #4 rebar to reinforce the new footer and extends the rebar into the earth at either end of the footing excavations so that when the area between the first set of new footers is excavated there will be something to tie into. Use Form-a-Drain for the form on the inside. Wait a month for the first set of blocks to cure and then go back and excavate the earth between each of those 4ft. sections and repeat the process until you've filled in all area between blocks. Connect your drain tile to the Form-a-Drain.

ONE TEAM - ONE FIGHT!!!

Mike

To do that, would he be digging from the outside as well? In which case, he could lay conventional perimeter drainage around the outside, right? Then would there be any need for interior drains? Better to stop the water at the exterior, I would think.
Link to comment
Share on other sites

Yes, but if he's already undermined the interior and at that point determined that there are no footers, excavating the exterior would risk toppling the entire foundation. If the basement is wet enough to have warranted an interior drain in the first place (and dependant upon soil conditions, water volume and pressure) he may have already significantly increased the risk of failure. Short of replacing the whole basement, Mike's got the right fix.

Last year there was a 1906 house near me that was excavated around for an addition. There was a moderate over night rain, and by the next morning one wall had fallen out from under the house. Slip formed concrete walls without footers.

Link to comment
Share on other sites

Have your contractor add a footer under the wall 4ft. at a time skipping every other 4ft. section. Make sure the contractor uses dobies and #4 rebar to reinforce the new footer and extends the rebar into the earth at either end of the footing excavations so that when the area between the first set of new footers is excavated there will be something to tie into. Use Form-a-Drain for the form on the inside. Wait a month for the first set of blocks to cure and then go back and excavate the earth between each of those 4ft. sections and repeat the process until you've filled in all area between blocks. Connect your drain tile to the Form-a-Drain.

ONE TEAM - ONE FIGHT!!!

Mike

The only thing I might add is to make sure that when you cast the new footing in under the foundation you should vibrate the concrete to eliminate any voids at the foundation to footing cold joint. You could easily have air pockets that will have waterproofing as well as structural repercussions.

Ramon

Link to comment
Share on other sites

Have your contractor add a footer under the wall 4ft. at a time skipping every other 4ft. section. Make sure the contractor uses dobies and #4 rebar to reinforce the new footer and extends the rebar into the earth at either end of the footing excavations so that when the area between the first set of new footers is excavated there will be something to tie into. Use Form-a-Drain for the form on the inside. Wait a month for the first set of blocks to cure and then go back and excavate the earth between each of those 4ft. sections and repeat the process until you've filled in all area between blocks. Connect your drain tile to the Form-a-Drain.

ONE TEAM - ONE FIGHT!!!

Mike

What are dobies, Mike?

Marc

Link to comment
Share on other sites

I'd assumed it was a basement or crawlspace. To underpin a wall like that, you have to do a whole lot of excavation on the exterior but from the interior you might have to go down only a foot to 18 inches max. On the exterior you have to deal with landscaping and then backfilling in lifts and tamping every six inches or so; from the interior, you pretty much just need to backfill and tamp once.

ONE TEAM - ONE FIGHT!!!

Mike

Link to comment
Share on other sites

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.

Guest
Reply to this topic...

×   Pasted as rich text.   Paste as plain text instead

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

×
×
  • Create New...